Q1problem
[25 marks]NovaTech Ltd contracts with DataStream plc for the installation of a bespoke IT system for £500,000. The contract contains a liquidated damages clause of £5,000 per day of delay and a clause limiting DataStream's total liability to £250,000. DataStream subcontracts the hardware installation to CircuitWorks Ltd. The system is delivered three weeks late due to CircuitWorks' incompetence. The system also contains a critical software bug that causes NovaTech to lose client data worth £800,000 in lost business. NovaTech had specifically informed DataStream of the importance of data security during negotiations. DataStream argues: (i) the liquidated damages clause limits recovery for delay; (ii) the limitation clause caps total liability; and (iii) CircuitWorks is responsible for the hardware issues. Advise NovaTech, considering the enforceability of both clauses and the privity issues.