IN THE HIGH COURT OF JUSTICE BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES TECHNOLOGY AND CONSTRUCTION COURT (QBD)
B e f o r e :
MR EDWARD PEPPERALL QC SITTING AS A DEPUTY HIGH COURT JUDGE ____________________
____________________
Mr Steven Walker QC (instructed by Mills & Reeve LLP) for the Claimant Miss Lynne McCafferty (instructed by Beale & Company Solicitors LLP) for the Defendant Hearing date: 25 January 2018 Judgment handed down: 5 April 2018 ____________________
HTML VERSION OF JUDGMENT APPROVED ____________________
Crown Copyright ©
MR EDWARD PEPPERALL QC:
This judgment concerns the trial of a preliminary issue as to whether these contribution proceedings are statute barred pursuant to section 10 of the Limitation Act 1980 . It raises a short point as to the proper construction of the section.
In 2001/2, the Claimant, R.G. Carter Building Limited, built a new science block at Boston Grammar School. Unfortunately, the science block, which was designed by the Defendant, Kier Building Services Limited, suffered problems with the ingress of water into the building. Consequently, the client, Lincolnshire County Council, brought arbitration proceedings against Carter. The arbitration was settled in 2015 upon terms that Carter would carry out remedial works at its own cost.
On 20 September 2017, Carter issued these proceedings against Kier seeking an indemnity or a contribution of £205,908.60 in respect of the cost of the settlement. Kier has not filed a Defence but plainly intends to plead that the claim is statute barred. In those circumstances, the court approved a consent order on 31 October 2017 setting down the trial of the preliminary issue of limitation. While it is unusual to conduct the preliminary issue of an unpleaded defence, the parties have jointly invited the court to take this course.
The parties entered into a standstill agreement on 28 April 2017. Of course, such agreement does not prevent Kier from arguing that this claim was already statute barred, but it does not seek to argue that the claim is out of time if the court finds that the limitation period had not expired at the date of the standstill agreement. Thus, the issue before the court is whether the contribution claim was statute barred on 28 April 2017.
The parties' respective positions can be briefly summarised:
Carter called two witnesses; its company secretary, Robert Alflatt, and its solicitor, Alison Garrett of Mills & Reeve LLP. Both had first-hand dealings with the 2015 settlement of the arbitration. They explained the negotiations that were conducted between Carter and the Council between December 2014 and June 2015. Specifically, they explained that an agreement in principle was reached during April 2015 but that all negotiations were expressly conducted on a subject to contract basis until the parties signed the settlement agreement on 29 June 2015.
Kier served a witness statement from its solicitor, Nathan Modell, of Beale & Company Solicitors LLP. Mr Modell described the negotiation of the standstill agreement in April 2017. Otherwise, he had no direct knowledge of the 2015 settlement and his statement essentially gave a preview of counsel's submissions. He was rightly not called to give oral evidence.
Carter and the Council attended a without prejudice meeting on 27 March 2015. Mr Alflatt attended on behalf of Carter together with David Drake (Carter's Director and General Manager) and Peter Smith (the then regional director responsible for Carter). A handwritten note of their discussions was produced in evidence. It recorded agreement that Carter would carry out external remedial works at its own cost as soon as reasonably practicable. The parties also agreed that Carter would carry out internal works at the joint cost of the parties, but the scope of such works remained to be agreed. In addition, John Radice was to provide a warranty in respect of his remedial design, the wording of which was to be agreed. The emerging agreement was expressly subject to the school's agreement.
Further correspondence followed in which the parties clarified what had been agreed on 27 March. Mr Alflatt agreed in cross-examination that the scope of the proposed external works had already been defined by reference to Mr Radice's December 2014 report. The proposed deal was not that Carter would undertake to remedy the defects, but that it would carry out the agreed works. It was therefore seeking to contract for a clean break with any warranty as to the efficacy of the design to be given by Mr Radice. Accordingly, it was important to the Council, and no doubt the school, that the proposed works would be effective.
Meanwhile, on 29 March 2015, Mr Drake e-mailed a detailed proposed specification for the internal works to the Council. In cross-examination, Mr Alflatt described the specification as a "draft for discussion."
By an e-mail dated 16 April 2015, prominently marked "WITHOUT PREJUDICE SAVE AS TO COSTS" and "SUBJECT TO CONTRACT", Mark Keal, a senior lawyer at the Council, wrote:
By a second e-mail sent on the same day, again prominently marked "WITHOUT PREJUDICE SAVE AS TO COSTS" and "SUBJECT TO CONTRACT", Mr Keal added:
By a letter dated 20 April 2015, Mr Keal proposed additional internal works. Such letter was sent under cover of an e-mail in which Mr Keal made clear that the Council considered it sensible to agree the scope of the internal works before finalising the heads of terms. This point was repeated in a further letter from Mr Keal on 21 April in which the Council sought a revised schedule of internal works.
The investigatory surveys were undertaken over the May Day bank holiday weekend. Mr Alflatt explained that the surveys were necessary in order to finalise the scope of the remedial works. Carter responded on 7 May 2015 on a number of issues, including points of detail about the scope of the internal works. A technical meeting was held on 8 May 2015 in the absence of the lawyers in order to discuss and agree the design and scope of the remedial works and the programme for the works to be undertaken over the summer holidays. Rejecting the suggestion that Carter had reached a concluded agreement with the Council by 16, or alternatively 28, April 2015, Mr Alflatt observed that it was not until the technical meeting on 8 May that there was clarity as to the scope of the works to be carried out.
Modest preparatory work started on site on 8 June 2015. Specifically, cabins were delivered to site and the risk assessment and method statement were finalised. Mr Alflatt said that he was then confident that agreement would be reached and that accordingly Carter was happy to undertake some preliminary work in setting up the site in view of the limited window in which remedial works could be undertaken before the start of the autumn term. Nevertheless, he maintained that the parties had not at that stage reached agreement as to the final scope of the works. Indeed, Mr Alflatt told me that the scope of the external works was adjusted right up until 25 June 2015 following sample work undertaken on 23 June upon opening up a section of the external wall.
Section 1 of Civil Liability (Contribution) Act 1978 provides that any person liable in respect of any damage can recover contribution from any other person liable in respect of the same damage. Section 1(4) of the Act provides:
Section 10(1) of the Limitation Act 1980 provides that no action to recover a contribution pursuant to the 1978 Act shall be brought after the expiry of a period of two years from the date on which such right accrued. The right to a contribution is treated for the purpose of limitation as accruing on the date of any judgment or award against the party seeking the contribution (s.10(3) of the 1980 Act) or upon agreement to pay compensation in the case of a settlement (s.10(4)).
Section 10(4) provides:
The issue in this case is whether time runs under section 10(4) only once the parties have entered into a binding agreement for the payment of compensation, as Mr Walker QC submits, or whether something short of a binding agreement is sufficient to start time running, as Miss McCafferty submits.
Before turning to this question, it is necessary first to consider the structure and general operation of section 10. In brief:
It was rightly common ground before me that sections 10(3) and (4) are mutually exclusive. Rix LJ considered this point in Aer Lingus , at [36]:
Miss McCafferty argued that section 10(4) does not require the parties to have entered into a binding agreement, and that an agreement in principle with the final details still to be worked through is sufficient to make time start running under the section. She developed the argument as follows:
Mr Walker QC submits that nothing less than a binding agreement can set time running. He argued:
Miss McCafferty's argument can be tested by considering the position that might arise if the parties reach an agreement in principle – perhaps, as here, a settlement that is expressly made on a subject to contract basis – and yet such agreement subsequently breaks down. On Miss McCafferty's argument:
I put this problem to Miss McCafferty. She did not shrink from the difficulty created by her construction and accepted that the consequence of time starting to run under subsection (4) upon the agreement of non-binding terms of settlement might well be that the case subsequently fell to be determined under subsection (3) upon the talks breaking down and the matter proceeding to trial.
In my judgment, this is not a sensible construction of the Act. It is important to approach the section on the basis that sections 10(3) and (4) are, upon their true construction, intended to be mutually exclusive. I agree with Rix LJ that there can only be one trigger date to start time running under section 10; namely either:
Since there can only be one trigger event, it follows that time cannot start to run where the parties reach an unenforceable agreement as to payment. In such a case, the litigation or arbitration remains on foot and time will only start to run under section 10(4) from the date of the subsequent formal agreement or, if the matter cannot be agreed, under section 10(3) from the date of the judgment or award.
In my judgment, Mr Walker QC is right therefore to submit that the proper construction of section 10(4) is that time only starts to run from the date of a binding agreement as to the amount of the compensation payment.
Further, I consider that such conclusion is obviously right when one considers the interplay between section 1(4) of the 1978 Act and section 10(4) of the 1980 Act. Since the cause of action for a contribution only arises under section 1(4) upon settlement of the underlying dispute, time cannot start to run under the Limitation Act 1980 from the date of some earlier non-binding agreement. In any event, if something less than a binding agreement suffices, it is entirely unclear what lower standard is to be applied.
I acknowledge that the passage in McGee cited by Miss McCafferty envisages that there might be cases in which time starts to run despite the parties' failure to agree all the details of their settlement. Knight and Chief Constable of Hampshire Constabulary were just such cases. The passage continues, after reference to Knight :
In my judgment, McGee is right to assert that the critical matter is whether there has been agreement as to the payment; indeed section 10(4) says as much. That must be the focus of the enquiry and not whether the parties have agreed ancillary matters. Further, I consider that McGee is right to say that the court will want to see evidence of a "finalised" rather than a preliminary agreement; although I should prefer to distinguish between a binding agreement and an incomplete agreement or an agreement in principle. I do not consider that there is any tension in those statements. Ordinarily, one might expect the parties not to reach a binding agreement as to payment until they have also agreed the other terms of their settlement. That said, it is beyond doubt that the parties are free to contract on such basis. In Pagnan SpA v Feed Products Ltd [1987] 2 Lloyd's Rep. 601, Lloyd LJ summarised the principles applicable in determining whether there is an immediately binding contract, at p.619:
Accordingly, it is open to the parties to reach an immediately binding agreement as to the settlement payment, but leave for later agreement details as to payment terms (as in Knight ) or any liability for costs (as in Chief Constable of Hampshire Constabulary ). In such cases, time will start to run from the date of the agreement as to the amount of the payment. Equally, it is open to the parties to agree that, to use an expression much used in connection with the current Brexit negotiations, nothing is agreed until everything is agreed. If so, time will not start to run until the date of the subsequent binding agreement as to the payment or, should agreement prove impossible, the judgment or award.
I am fortified in these conclusions by the decision of Judge Havery QC in Baker . In that case, a settlement offer expressly made on a subject to contract basis was accepted by a letter dated 3 March 2005. The parties then executed a formal settlement agreement. Judge Havery QC held that time ran from the date of the execution of the settlement agreement on 11 March 2005.
It will be evident from my earlier review of the evidence that the negotiations during April 2015 were expressly conducted on a subject to contract basis. It was common ground between counsel that parties negotiating on such a basis will generally be presumed to intend that they should not be bound unless and until they subsequently enter into a formal written contract: Rossdale v Denny [1921] 1 Ch. 57. Accordingly, Miss McCafferty rightly conceded in her closing submissions, and I find, that there was no binding agreement between Carter and the Council by 28 April 2015. Binding terms as to the payment in kind were only agreed upon the execution of the settlement agreement on 29 June 2015.
In view of this finding and my conclusions as to the proper construction of section 10(4), it follows in my judgment that this contribution claim is in time.
Having, however, heard the evidence and further argument, I briefly set out my conclusions in the event that I am wrong as to the proper construction of the section. Even if a non-binding agreement is sufficient to make time run, there was not, in my judgment, agreement as to the "payment" to be made until after 28 April 2015:
The contribution claim was therefore brought in time and the limitation defence fails.