A. Admissibility
B. Merits
II. APPLICATION OF ARTICLE 41 OF THE CONVENTION
“If the Court finds that there has been a violation of the Convention or the Protocols thereto, and if the internal law of the High Contracting Party concerned allows only partial reparation to be made, the Court shall, if necessary, afford just satisfaction to the injured party.”
A. Damage, costs and expenses
B. Default interest
FOR THESE REASONS, THE COURT UNANIMOUSLY
(a) that the respondent State is to pay the applicant, within three months from the date on which the judgment becomes final in accordance with Article 44 § 2 of the Convention, EUR 1,400 (one thousand four hundred euros) in respect of non-pecuniary damage, to be converted into the national currency of the respondent State at the rate applicable at the date of settlement, plus any tax that may be chargeable;
(b) that from the expiry of the above-mentioned three months until settlement simple interest shall be payable on the above amount at a rate equal to the marginal lending rate of the European Central Bank during the default period plus three percentage points;
Done in English, and notified in writing on 18 February 2010, pursuant to Rule 77 §§ 2 and 3 of the Rules of Court.
Claudia Westerdiek Peer Lorenzen
Registrar President