Skip to main content

Free · SQE1 Question of the Day

Today's SQE1 question

One worked single-best-answer question, free, every day. Answer it, then reveal the correct option and the cited rationale.

contractContract Law — Consideration; existing contractual duty rule; Stilk v Myrick; Williams v Roffey Bros

Danielle, a professional decorator, agrees in writing to repaint Owen's house for £4,000, with the work to be completed by 1 June. On 20 May, Danielle tells Owen she cannot finish by 1 June unless he pays an extra £800. Owen, who has guests arriving on 2 June and faces no penalty clause or difficulty finding a replacement, reluctantly agrees to pay the extra amount solely to ensure timely completion. Danielle completes the work on time. Owen refuses to pay the additional £800. Advise Owen.