B e f o r e :
THE HONOURABLE MR JUSTICE HENSHAW ____________________
____________________
Michael Nolan QC (instructed by W Legal Limited) for the Claimant Angharad M Parry (instructed by Studio Legale Associato Ridolfi Ghigi Longanesi) for the Defendant Hearing date: 16 December 2020 Judgment Approved ____________________
HTML VERSION OF JUDGMENT APPROVED ____________________
Crown Copyright ©
Mr Justice Henshaw:
(A) INTRODUCTION
(B) BACKGROUND TO THE DISPUTE
(1) Contract and Vessel Nomination
(2) The Award
(3) The Appeal and the Challenge
(C) APPEAL QUESTION 1: WAS THE MAKING OF A "FALSE" NOMINATION A BREACH OF CONDITION?
(D) APPEAL QUESTION 2: OBLIGATION TO NOMINATE A VESSEL ALREADY CHARTERED
(E) APPEAL QUESTION 3/FIRST SECTION 68 ISSUE: OBLIGATION TO PROVIDE COPY CHARTERPARTY
(F) SECOND SECTION 68 ISSUE: CUMULATIVE EFFECT OF BREACHES
(G) APPEAL QUESTIONS 4 AND 5: INTEREST
(H) CONCLUSION
(A) INTRODUCTION
The Claimant (" Sellers ") sold a cargo of Ukrainian feed corn under a contract dated 13 December 2017 (the " Contract ") to the Defendant (" Buyers "). A dispute arose, which the parties referred to a GAFTA tribunal, who decided in favour of the Buyers. The Sellers appealed to a GAFTA Board of Appeal (the " Board "). The Board issued an award dated 19 March 2020 (the "Award ") in favour of the Buyers. The Sellers now appeal, pursuant to permission granted by Teare J, on five questions of law under section 69 of the Arbitration Act 1996 (the "Act "). There is also a challenge to the Award under section 68(c) and (d) of the Act on the ground that the Board did not deal with two issues put to it.
For the reasons set out below, I have concluded that the Award should stand and that the challenge and the appeal under sections 68 and 69 of the Act should be dismissed.
(B) BACKGROUND TO THE DISPUTE
(1) Contract and Vessel Nomination
By the Contract, the Sellers agreed to sell to the Buyers 25,000 mt +/- 5% at Buyers' option Ukrainian Feed Corn in Bulk, crop 2017, FOB 1 safe berth/1 safe Ukrainian port, Yuzhny, Odessa or Chernomorsk. The Contract included the following provisions:
ETA
VESSEL'S NAME AND AGE
FLAG
DIMENSIONS OF THE VESSEL (LOA/BEAM/DM)
OWNERS NAME
DWT
AIRDRAFT
DEMURRAGE/DESPATCH RATE
IMC
COUNTRY OF DESTINATION
ESTIMATED QUANTITY TO BE LOADED"
GAFTA Form 49 clause 6 (" Period of Delivery ") provides:
The Buyers nominated the M/V " Tai Hunter " ("the Vessel ") on 20 March 2018. The nomination gave an ETA of 1 April 2018 AGW WP (all going well, weather permitting) and the destination as Egypt. The nomination failed to provide the owners' name as required by the Pre-Advice clause in the Contract.
The Sellers were informed by a third party that day that the Vessel had berthed at the Olimpex Terminal in Odessa and was due to complete loading on 21 March 2018. The message indicated that the Vessel was then due to sail directly to Ireland without going via any Ukrainian ports: as indicated below, the Board found that information to be incorrect.
In view of this information, the Sellers, via the parties' respective brokers, asked the Buyers for a copy of the charterparty in respect of the prospective voyage. The Buyers stated that the message had been sent up the contractual chain to their sub-buyers, and they would revert once they had received the answer. The Buyers asked the Sellers to nominate the load port and agents.
The next day, the Sellers' agents sent another message to the Buyers indicating that they had doubts over the genuineness of the nomination. The agents added that they were confident that the Sellers' silence in not nominating the loading port would not cause any harm, since it appeared that the Vessel would not be in Ukrainian Black Sea waters on 1 April 2018.
Over the following days, the parties exchanged further messages, with the Sellers demanding sight of the charterparty for the Vessel and the Buyers demanding the nomination of load port and agents. On 26 March 2018, the Sellers purported to terminate the contract for repudiatory breach:
On 28 March 2018, following continued dialogue between the parties, the Buyers purported to nominate a substitute vessel, the M/V " Mariana ", with an ETA of 5 April 2018 AGW WP. The nomination gave the destination as Portugal and asked for details of the load port, load port agents and surveyors.
The Sellers did not accept the revised nomination of the Mariana :
Also on 28 March 2018, the Buyers sent a further message to the Sellers substituting MV " Mariana " with MV " Deribas " with an ETA of 8 April 2018 AGW WP. The nomination gave the destination as Portugal and asked for the load port, load port agents and surveyors. On 29 March 2018 the Sellers responded that in the light of their response to the substitute nomination of " Mariana ", the relevance of Buyers' message relating to " Deribas " was unclear.
By 3 April 2018, both parties accepted that the contract was at an end, and the Buyers wrote that:
The parties provisionally settled their dispute the following day by an agreement (the " Settlement Agreement " ) under which the Buyers purchased the corn at an increased price of US$190 pmt but otherwise on the same terms. Clause 3 of the Settlement Agreement provided for a price variation in the event of a dispute under the original contract:
(2) The Award
In the Award, the Board considered five issues:
The Board found that the nomination of the Vessel was not manifestly false in the sense described in Texaco v Eurogulf ('The Giray') [1987] 1 Lloyd's Rep 541, a decision of Hirst J to which I return below. In Texaco it had been physically impossible for the vessel to reach the loadport during the delivery period. The Board stated, after referring to Texaco :
The Board then referred to the facts in more detail regarding the Vessel's movements, including the Sellers' submission that Egyptian ports are notorious for congestion, and the fact that, on the date the Vessel reached Egypt, information received from the Alexandria Port Authority indicated that the delay there was between 24 and 43 days. Ultimately, having presented notice of readiness at Alexandria on 26 March 2018, the Vessel did not in fact depart from there until 21 days later, on 16 April 2018, after the expiry of the contractual delivery period.
The Board concluded that the Buyers' nomination on 20 March 2018 of the "Tai Hunter" was invalid because the ETA provided was unreasonably ambitious:
The Board did not, however, consider that this was a breach of condition which entitled the Sellers to terminate the contract:
The reference in § 11.23 to Roskill LJ was to his judgment in Cehave N.V. v. Bremer Handelsgesellschaft m.b.H . (" The Hansa Nord") [1976] Q.B. 44, [1975] 2 Lloyd's Rep. 445 (CA).
Accordingly, the Board concluded on this issue:
As to whether the Vessel had been chartered by the time of nomination, the Board said:
The Board found that the Buyers were in breach by their failure to send a copy of the charterparty of the Vessel, as they were under a contractual obligation to provide the charterparty "at their first request" , but not entitled to damages. The Board noted that the Buyers had by 26 March 2018 not provided a copy of the Tai Hunter charterparty following the Sellers' request on 21 March. The Board continued:
Accordingly, the Buyers were successful in their claim and were awarded US$ 325,762.50. An issue then arose about interest:
(3) The Appeal and the Challenge
The questions of law on which the Sellers were given permission to appeal are as follows:
i) Is the obligation on the buyer of goods FOB not to make a false nomination of a vessel (i.e. one of a vessel that, at the date of nomination, is incapable of arriving at the loadport at or around the ETA provided or within the delivery period) a condition, breach of which entitles the seller to terminate the contract?
ii) On a true construction of the Contract, were the Buyers obliged to nominate a vessel which had been chartered by them or by their sub-buyers at the date of nomination?
iii) Was the obligation of the Buyers to provide a copy of the Charterparty, by which the vessel nominated had been chartered, to the Sellers " at their first request " a condition, breach of which entitled the Sellers to terminate the Contract?
iv) Can a Tribunal lawfully exercise its discretion under section 49 of the Arbitration Act 1996 by awarding interest to run from a date earlier than the date when the losing party's obligation to pay the principal sum found due arose and, if so, in what circumstances?
v) Having found that the Sellers were liable to the Buyers under the terms of the Settlement Agreement, was the Board wrong in law to award interest from the 4 April 2018 rather than from the date when, according to the Settlement Agreement, that sum became due to the Buyers?
The Buyers point out that the court's approach on a section 69 appeal should be a cautious one. The court's starting point should be to show deference to the arbitral tribunal. The Award should be read " in full in a fair and reasonable way and should not be subjected to minute textual analysis. The courts do not approach awards with a meticulous legal eye endeavouring to pick holes, inconsistencies and faults or with the object of upsetting or frustrating the process of arbitration ." (see, e.g., Progress Bulk Carriers Limited v Tube City IMS L.L.C [2012] EWHC 273 (Comm) §13, quoting Pace Shipping Co v Churchgate Nigeria [2010] 1 Lloyds Law Rep page 183 § 16).
There is also a section 68 appeal on the following grounds:
i) the Board did not answer the question set out at 24.iii) above; and
ii) the Board failed to answer the question of whether the Buyers were in repudiatory breach of contract or renounced the contract by, cumulatively, (a) making a nomination of a vessel which was false, (b) failing to name the owners of the Vessel when they nominated it, (c) nominating a vessel which neither they nor their sub-charterers had chartered and (d) failing to provide a copy of the charterparty at the Sellers' first request.
(C) APPEAL QUESTION 1: WAS THE MAKING OF A "FALSE" NOMINATION A BREACH OF CONDITION?
The Sellers say that the Board was correct to find that the ETA should have been given honestly and on reasonable grounds and that the nomination of the Tai Hunter was accordingly ' not valid' ; however, the Board should further have concluded that that obligation was a condition, breach of which entitled them to terminate. The failure so to conclude was, the Sellers submit, contrary to authority.
The Buyers accept that where time is of the essence, strict compliance with the time for performance is a condition of the contract, any breach of which will entitle the innocent party to elect to terminate the contract. However, where the obligation is to perform within a timeframe, a party whose performance is defective is entitled to correct that performance provided that it does so within the contractually allotted period (see, e.g., Apps, " The Right to Cure Defective Performance" (1994) LMCLQ 525).
It is well established that where an ETA is incorporated as a term of a sale contract, there is a breach of condition if that ETA has not been given honestly and on reasonable grounds.
For example, in Sanday v Keighley Maxsted [1922] 10 Lloyd's Rep 738, buyers refused to take up shipping documents on the ground that the contracts of sale had provided that the goods would be "[e]xpected ready to load late September" . The goods were not ready, and the issue was whether the buyers were entitled to terminate the contract on that basis. Counsel for the respondents submitted that there were three possible meanings of the term: first, (objectively) that the vessel was in a position to load in late September; secondly, (subjectively) that " expected means expected by the seller and does not refer to expectation by the shipping world generally or any reasonable man who knew the circumstances "; or, thirdly (" even more subjective" ) that the seller honestly but perhaps without any ground whatever expected the vessel to be ready to load late September (p740 LHC). The Master of the Rolls concluded:
Similarly, Christopher Clarke J in The Azur Gaz [2006] 1 Ll. Rep. 163 § 42 followed Sanday and The Mihalis Angelos (see below) in holding that the seller's obligation under a CIF contract to give the ETA (stated as a term of the contract) of the named vessel at the loadport honestly and on reasonable grounds is a condition.
The same principle applies to ETAs set out in charterparties. In Evera SA Comercial v North Shipping Company Ltd [1957] 2 Lloyd's Rep 367, Devlin J said:
In The Mihalis Angelos [1971] 1 QB 164 a vessel was chartered to carry mineral ore from Haiphong to a North European port. The vessel was described in the charterparty as ' expected ready to load under this charter about July 1 1965 '. The charterparty provided for an option to cancel the contract should the vessel not be ready to load on or before 20 July 1965. The vessel remained at Hong Kong between 23 June and 17 July 1965, when the charterers purported to cancel the charterparty on grounds of force majeure. The owners purported to accept that cancellation as a repudiation of the contract. The Court of Appeal held that the expected readiness clause was a condition, which the owners had broken on 25 May 1965 when they could not reasonably have expected that the ship would be ready to load on 1 July. In those circumstances it was conceded that the charterers had been entitled to treat the contract as having come to an end on 17 July (despite having purported to cancel on different grounds). Lord Denning MR said:
It is evident that the Master of the Rolls made his finding on two bases: misrepresentation and repudiation. However, it is clear from the other judgments that the expected readiness clause was regarded as a condition. Edmund Davies LJ put it thus:
Megaw LJ made essentially the same point:
Thus, where a party to a charterparty provides an ETA as a term of the charterparty, it is a condition that he does so on honest and reasonable grounds.
The cases relating to the situation where a buyer is required to nominate a vessel pursuant to a term of a sale contract, where the possibility of substitution nomination arises, have developed somewhat differently.
In Agricultores Federados Argentinos Sociedad Cooperative Limitada v Ampro SA Commercial Industrielle et Financiere [1965] 2 Lloyd's Rep 157 (" Ampro ") the sellers sold the respondent buyers 2000mt maize fob for delivery between 20 and 29 September 1960 without extension. The buyers nominated the vessel Oswestry Grange due on 26 September. However, it appears that, in circumstances that are somewhat unclear, the vessel had not arrived by 29 September and was due to arrive only the next day. The buyers, thinking that this was only slightly outside of the delivery window, were largely unconcerned. However, coincidentally, there was a rise in the market and, at the last minute, on 4pm on 29 September, the sellers informed the buyers that the sellers intended to cancel the contract owing to the inability of the Oswestry Grange to load in contract time. In a somewhat fortuitous turn of events, by 4.30pm the buyers had made arrangements for a new vessel, the Austral, to receive the cargo that same day. Widgery J held that that was a valid nomination:
It will be noted, though, that that reasoning proceeded on the footing that there was no express obligation to nominate a vessel, the nomination being no more than a courtesy.
In Bremer Handelsgesellschaft M.B.H v. J. H. Rayner & Co. Ltd [1978] 2 Lloyd's Rep 73, the sellers sold the buyers 6800 tonnes of Brazilian soya beans for shipment July 1974. The contract incorporated the terms of the standard FOB contract of ANEC (the Brazilian Grain Exporters Association), § 7 of which provided for the buyers to nominate the vessel "to Sellers in writing in time for Sellers to receive with minimum 15 days ' notice of earliest readiness of tonnage at…port of loading" . The ANEC form in turn incorporated the GAFTA 64 terms, § 7 of which provided that "Should Buyer not tender suitable tonnage within contract time he shall be in default unless he gives notice to the Seller ... not later than the last day of the specified period for the delivery that an extension is claimed" .
On 15 July, the buyers nominated a vessel (the Nestos ) to lift part of the cargo, with ETA 27 July, i.e. giving less than 15 days' notice. On 19 July the buyer nominated another vessel to lift part of the cargo with ETA 3 August, i.e. outside the July 1974 shipment window, and by separate letter sought an extension under GAFTA § 7. On 22 July the sellers rejected both nominations as not being in accordance with § 7 of the ANEC form, and treated the contract as having come to an end.
At first instance, Mocatta J noted that the major question of law in the case was whether the extension provisions of GAFTA § 7 formed part of the contract between the parties, but he also made a number of findings on other matters. He stated:
Mocatta J continued:
Mocatta J then referred to Finnish Government (Ministry of Food) v H Ford & Co (1921) 6 Lloyd's Rep 188, where the Court of Appeal had held that a term of a sale contract that the buyers would ship by steamers "expected ready to load February and/or March 1920" was a condition of the contract. Mocatta J noted that that case had been followed in The Mihalis Angelos , and also cited Tradax Export v Andre & Cie [1976] 1 Lloyd's Rep 416 (where Lord Denning MR had stated that the words " without delay " in clause 21 of GAFTA 100, dealing with force majeure , denoted a condition of the contract). Mocatta J concluded that in the light of these authorities it was:
unless the buyers were saved by a finding the arbitrators had made regarding trade custom (which, Mocatta J held, they were not).
Finally for present purposes, Mocatta J concluded on this issue:
Mocatta J's decision in Bremer v Rayner was reversed on other grounds, the Court of Appeal concluding that the buyers could rely on the extension provision ([1979] 2 Ll. Rep. 216). However, in the context of damages the Court of Appeal nonetheless had to consider whether the buyers could and would have replaced their initial bad nomination with a good one. Bridge LJ recorded Mocatta J as having held that "it was a condition of a valid nomination of any vessel under c. 7 of the Anec form that a full 15 days' notice of her earliest date of readiness to load should be given at the time of nomination by the buyers to the sellers". After quoting the passage quoted in § 44 above, Bridge LJ continued:
Bridge LJ thus made clear that an initial bad nomination, giving insufficient notice, could be cured by a subsequent good nomination. That view was also reflected in his conclusion on the question of damages:
Similarly, Templeman LJ concluded, as to damages, that it was sufficient for the buyers to show that, as at the date (29 July) on which they accepted the sellers' repudiation of the contract, it remained possible for the buyers to fulfil their contractual obligations by a valid nomination of the Nestos in time for delivery on 21 August, and that they intended to take delivery on that vessel on the first day she became available (p.228 lhc). Megaw LJ did not find it necessary to decide whether clause 7 of the Anec form was a condition; but even assuming that it was, he concluded that at the time the sellers' repudiation of the contract occurred and was accepted, there was ample time for the defective nomination of the Nestos to be replaced by a valid nomination of a vessel to lift the relevant part of the cargo (p.229 rhc).
Subsequently, in Bunge v Tradax [1981] 1 WLR 711 Lord Roskill endorsed Mocatta J's conclusion on the nature of clause 7 of the Anec form:
It was unnecessary for Lord Roskill to consider any issue relating to substitute nomination.
The Sellers rely on the general statements of principle in Bunge as to when a stipulation as to time will be a condition of a contract. In that case, the sellers sold 15,000 tons of soya bean meal on GAFTA terms requiring 15 days notice of readiness of vessel(s). The issue was whether the giving of timely notice of readiness was a condition, the House of Lords concluding that it was. Lord Roskill, who gave the leading judgment, stated:
Lord Wilberforce added:
Lord Lowry said this:
The Sellers make three main submissions of principle based on Bunge:
i) The pre-advice clause is a time clause in a mercantile contract in respect of which there is a need for certainty. The court will require precise compliance with stipulations as to time wherever the circumstances of the case indicate that this will fulfil the intentions of the parties.
ii) There was an interdependence of obligations: until the Buyers had performed their obligation to nominate the vessel, the Sellers were not able to make arrangements to load the vessel and ultimately to load her when she arrived.
iii) The Contract was part of a string, which underlines or augments the need for certainty so that all parties can know where they stand.
The Sellers add that a false nomination is liable to put the seller to unnecessary expense, moving the goods to a particular port by the ETA, and is also liable to erode the trust between the parties: if an unreliable or ' unreasonably ambitious' nomination and ETA are given, what reason is there to believe the next nomination will be any better?
In principle I am inclined to agree that, for the reasons the Sellers put forward, it is a condition of the contract that the buyer has provided a valid nomination by the requisite time, thus enabling the seller to make the necessary arrangements with the goods. It does not follow, however, that (a) the pre-advice obligation also imports a negative obligation, viz not to make any prior 'false' nomination, or (b) that any such implied negative obligation is itself a condition of the contract. I leave on one side the category of cases referred to in Texaco (considered below) as 'Mickey Mouse' nominations, i.e. nominations not made in good faith of vessels which very obviously could not possibly reach the loadport on time. A nomination of that kind may be renunciatory and entitle the seller to treat the contract as at an end for that reason. Those cases apart, I am not persuaded that either the case law or considerations of principle require the nomination of a vessel in good faith but, objectively, without reasonable grounds, to be treated as a breach of condition entitling the seller to bring the contract to an end even in circumstances where a valid replacement nomination could in practice still be made.
I note that the Apps article cited earlier suggests, quoting a statement by Professor Goode, that "a justifiable loss in confidence in the seller resulting from the initial defective tender" may entitle a buyer to treat the contract as at an end: followed by a summary of Texaco v Eurogulf . The present Sellers suggest that the same reasoning may be applied to a buyer who has made an invalid nomination of a vessel. In my view that is the case only if and to the extent that the nomination is such as to evince a refusal or inability to perform the contract: see above.
It is true that a nomination made without reasonable grounds has the potential for putting the seller to unnecessary expense. Benjamin's "Sale of Goods" (11 th ed.) § 20-056 considers whether the seller might have a remedy in such circumstances:
Be that as it may, there is an inherent risk in any event that the buyer may make a last-minute substitution, even where the first nomination is valid, either through choice or because the vessel first nominated has unexpectedly turned out to be unable to meet the lifting deadline. The contractual timetable for the buyer's vessel nomination will be designed to give the seller sufficient time to arrange the provision of the goods. Provided a valid nomination is ultimately given by the applicable deadline, it should be possible for the contract (and the other contracts in any string) to be fulfilled without difficulty.
The possibility that a prior invalid nomination will cause additional expense to the seller also exists in cases such as Bremer v Rayner of 'non-contractual' nominations, yet did not in that case result in the seller being entitled to bring the contract to an end. The Sellers in the present case contend that a non-contractual nomination of that kind can simply be ignored, and thus will not put the seller to additional trouble or expense. However, the Sellers are constrained to accept that the position is the same where an apparently valid nomination is given (honestly and on reasonable grounds) but unforeseen circumstances result in a substitute nomination having to be given; or indeed where a valid nomination is given which the buyer simply chooses to substitute. It might be argued that those situations too can be distinguished, based on the greater culpability of a buyer who (as in the present case) gives a 'false' nomination honestly but without reasonable grounds. However, whilst there may be a case for regarding such a nomination as a breach sounding in damages, I do not believe that either authority or considerations of principle require it to be regarded as a breach of condition: provided, always, that a valid nomination is ultimately given in accordance with the contractual timetable.
There is also some force in the Buyers' point that the Sellers' contention would lead to the odd result that a buyer who makes an honest but over-ambitious initial nomination, and then substitutes it immediately with a valid nomination capable of timely performance, would be treated more harshly than a buyer who makes a valid initial nomination which is falsified by events yet who leaves it to the last moment to substitute it (or, one might add, a buyer who at the last permissible minute simply elects to nominate a replacement vessel and ETA).
Much of the argument at the hearing before me centred around the decision of Hirst J in Texaco v Eurogulf [1987] 2 Lloyd's Rep 541. There, the contract stipulated that the vessel's nomination by the buyers, Eurogulf, must be acceptable to the sellers, Texaco. The buyers nominated the Giray on 5 February 1986 and the sellers accepted that nomination the next day. The buyers on 7 February provided an ETA of 11-13 February at Milford Haven. However, on 10 February it was ascertained that the vessel was at Istanbul. On 11 February the buyers telexed the sellers advising that they had been a victim of fraudulent misrepresentation by their own buyers and would be unable to perform the contract:
The sellers regarded that telex as a repudiation, which they accepted, and subsequently sought summary judgment against the defendants. Hirst J rejected a submission that the sellers had renounced the contract by a previous telex, and concluded that the buyers' telex quoted above was repudiatory. Hirst J also went on to consider the sellers' alternative argument, that the "manifestly false nomination" of the Giray was itself a breach which gave rise to a right to terminate:
It was common ground that it was physically impossible for the Giray to reach Milford Haven by 13 February. The buyers submitted that the nomination was valid on its face, not self-evidently impossible and not known at the time to be other than good. In any event, the buyers argued, they had a right to withdraw the nomination and substitute a different vessel so long as the substitute could be tendered in accordance with the contract. Particular reliance was placed on the Ampro decision which I have considered above. That argument was rejected:
The Sellers in the present case submit that the principle to be extracted from Texaco is that it is a condition that any nomination is not false , i.e. that a nomination is made honestly and on reasonable grounds. Falsity in that sense, the Sellers contend, is to be distinguished from (a) a non-contractual nomination i.e. one which did does contain the information required by the contract, or fails (as in Bremer v Rayner) to give the notice period required by the contract, and (b) a nomination which is correct when given but is falsified by subsequent events.
I do not, however, consider Texaco to be authority for the proposition that a false nomination in the sense indicated above is per se a breach of condition which entitles the seller to treat the contract as having come to an end, precluding the buyer from any possibility of replacing it with a valid nomination. As the Buyers point out, the buyers in Texaco had evinced an intention not to be bound by the contract, by both the manifestly false nomination and by their telex saying expressly so. Further, Hirst J concluded that, on the facts before him, any question of a second, valid, nomination was fanciful. In distinguishing Ampro , Hirst J pointed out that in that case there had been a real, actual and potentially effective substitution of a second vessel. Hirst J did not state, or in my view imply, that any second nomination would have come too late if the seller had by then purported to accept the initial false nomination as bringing the contract to an end.
More recently, in Ramburs v Agrifert [2015] EWHC 3548 (Comm) Andrew Smith J said:
The relevant issue in Ramburs was the validity of the replacement nomination, but insofar as the passage quoted above expresses the general point that a nomination once made can be replaced so long as the second nomination is timely, it supports in my view the points made in § 58 above.
Counsel for the Buyers informed me that, following Ramburs, GAFTA revised its nomination clause to confirm that pre-advice terms for an original nomination do not apply to a substitute vessel: thus seeking to facilitate the making of substitute nominations.
The Buyers also cite the statement in Benjamin § 20-57 that:
The general proposition thus stated is in my view supported by the Bremer v Rayners , as discussed earlier, as well as Ampro . For completeness, however, I note that Benjamin also cites in support Modern Transport Co Ltd v Ternstrom and Roos [1924] LLR 345. The claimants in that case sold the defendants a shipment of coal FOB Hull, Grimsby or Immingham. The parties had separately sought to arrange another contract for the sale of coal to be shipped at Goole, though no contract had been finalised, and the ship Hernodia had been mentioned in that context. The buyers then telegraphed the sellers to ' load Hernodia contract 35 confirm' . In due course the Hernodia arrived at Goole. The issue was whether that telegram was a valid tender of the vessel. Rowlatt J held that it was:
I cannot see that this decision addresses the proposition for which the editors of Benjamin cite it: it sheds no light on the matter either way. Nonetheless, as indicated earlier, the proposition stated in Benjamin is in my view correct.
I conclude that the relevant principles are as follows:
i) Where a contract of sale requires the buyer to nominate a vessel by a particular date (including by stipulating a notice period and a shipment period), then it is (subject to any contrary intention expressed in the contract) a condition of the contract that the buyer provide a valid nomination by the relevant deadline. That is a stipulation as to time in a mercantile contract in relation to which the parties should be taken to have intended time to be of the essence.
ii) Accordingly, if by the latest date on which a valid nomination could be made the buyer has failed to provide one, then there is a breach of condition that will entitle the seller to treat the contract as being at an end.
iii) A valid nomination is one made honestly and on reasonable grounds, and otherwise in accordance with the contract terms.
iv) A valid nomination may be preceded by an initial nomination that is or becomes invalid, because either (a) it is 'non-contractual' in the sense of failing to provide the contractually stipulated notice period, or stating an ETA outside the contractual shipment window, (b) it is not made both honestly and on reasonable grounds, or (c) it becomes invalid due to subsequent events e.g. unforeseeable delays.
v) The giving of the initial invalid nomination is not in itself a breach of condition: no breach of condition occurs provided that a valid and timely nomination is given in due course.
vi) An initial invalid nomination made otherwise than honestly and in good faith (e.g. of a vessel which the buyer knows could not possibly meet the contractual lifting deadline) may evince an intention not to perform the contract, and thus entitle the seller to treat the contract as having been renounced by the buyer.
vii) It is unnecessary to decide in the present case whether, and if so in what circumstances, a prior invalid nomination could amount to a breach of contract sounding in damages, no such claim having been advanced or arising on this appeal.
I therefore consider that the Board in the present case was entitled to reach the conclusion to which it came. As the Board found, the Buyers had further time to make a valid nomination before the end of the delivery period; and the Buyer in due course did so. The initial nomination of the " Tai Hunter " was not a breach of condition entitling the Seller to treat the contract as having come to an end.
Accordingly, I dismiss this aspect of the section 69 appeal.
(D) APPEAL QUESTION 2: OBLIGATION TO NOMINATE A VESSEL ALREADY CHARTERED
The Sellers submit that the Contract required the Buyers to nominate only a vessel that they or their sub-buyers had already chartered. They say that this is clear from the obligation to provide a copy of the charterparty 'at first request' . If the vessel nominated had not been chartered, that obligation could not possibly be complied with.
The Buyers say that the question is moot. As noted earlier, the Board held that it did not have sufficient evidence to make a finding as to whether the Tai Hunter was fixed at the time of nomination. Teare J struck out the Sellers' section 68 challenge alleging a failure by the Board to deal with the issue of whether the Buyers were in breach (including breach of condition or repudiatory breach) by nominating a vessel that had not been fixed to them or their sub-buyers at the date of nomination. Teare J noted that "where the tribunal says that there is no sufficient evidence to support the fact alleged, there is no real prospect of establishing a serious irregularity within section 68".
In these circumstances, I agree with the Buyers that the determination of the question of law could not affect the outcome of the case, because the position would remain that no factual basis for the alleged breach had been established. It would not therefore be appropriate to remit the Award (or any part of it) to the Board or a fortiori to vary or set aside the Award (or any part of it).
For completeness, however, I go on to consider the Board's conclusion on the point of law. They held that " a buyer is obliged to nominate only a ship which had either been fixed or had a reasonable expectation of being fixed" (Award § 11.34). Neither the Board nor the parties cites any authority on the point.
The Sellers object, first, that a 'reasonable expectation' might be of fixing in a week, a month or three months. Conversely, however, the buyer might have every reason to expect that the intended charterparty is on the verge of being fixed. The Seller's construction of the Contract would mean that that buyer was nonetheless in breach of condition. In my view the critical question is what needs to happen in order for the contract to work and for the parties to have the requisite degree of certainty about how it is to work. The seller's essential need in this context is for a valid and timely nomination to be given, and for the nominated vessel then to arrive on time ready to lift the cargo. The buyer's obligation to bring that about in itself requires sufficiently timely and effective steps to be taken to secure the vessel. I do not consider it possible to infer that the parties intended to go further by requiring, as a condition of the contract, that the charterparty actually be fixed at the time of the nomination.
Secondly, the Sellers make the related point that if the vessel has not yet been fixed, then the Buyer will be unable to provide a copy of the charterparty at the Seller's "first request" as required by the Contract. I consider this latter obligation in section (E) below, concluding that the requirement to provide a copy of the charterparty is not a condition of the contract. I do not consider that the obligation to provide a copy of the charterparty on the Seller's "first request" leads to the conclusion that the charterparty must have been fixed by the date of the nomination. Rather, where the charterparty remains to be fixed, the obligation must be construed as being to provide, following the Seller's request, a copy of the charterparty as soon as the fixture has been made.
I therefore dismiss the section 69 appeal on this point too.
(E) APPEAL QUESTION 3/FIRST SECTION 68 ISSUE: OBLIGATION TO PROVIDE COPY CHARTERPARTY
In this section I consider the section 69 appeal on this point, and the first of the two section 68 challenges.
The Sellers' primary case is that the Board failed to consider whether the failure to provide a copy of the charterparty at first request was a condition; and that that amounted to a serious irregularity being a "failure by the tribunal to deal with all the issues that were put to it" (section 68(d)) and/or a "failure by the tribunal to conduct the proceedings in accordance with the procedure agreed by the parties" (section 68(c)). The parties had agreed to arbitration in accordance with the GAFTA Arbitration Rules (no.125) incorporated into the Contract, which provide that the Board will "determine all the issues put before them" . The Sellers submit that the Board's conclusion "whilst Sellers have succeeded on this point, Buyers are not liable to them in damages" begs the question of whether the obligation was a condition.
By way of comparison, the Board stated the issues in relation to the nomination questions in this way:
By contrast, the issue about failure to send a copy of the charterparty was simply stated as "Were Buyers in breach of contract by their failure to send a copy of the charterparty of the vessel?"
The Buyers say it is nonetheless tolerably clear that the Board concluded that the term was not a condition, and suggest that the Sellers are taking a meticulous and overly minute approach to the Award. In considering the nomination obligation, the Board found that it was "not a breach of condition ": that language is to be contrasted with the Board's statement that the failure to provide a copy of the charterparty was "a breach of contract" , implying that the Board did not regard it as a breach of condition. Further, the Sellers asked the Board to clarify the Award under section 57 of the Act, receiving the response that the question had been answered "either expressly or by referral to those issues within the body of the Award".
The Board's reasoning on this issue is set out in Award §§ 11.36 and 11.37, quoted in § 22 above.
The references in Award § 11.37 to the Sellers having purported to terminate the Contract on the nomination ground, and to their failure to accept a substitute nomination or to nominate a load port, appear to indicate that the Board thought any question of the Buyer's failure to provide a copy charterparty being a breach of condition would be moot. The Buyers point out that it is not a serious irregularity for arbitrators to decide a logically anterior issue such that the further issue does not arise: see Home Secretary v Raytheon [2014] EWHC 4375 § 33(x). On that approach, however, it would have been necessary to decide that the copy charterparty issue was indeed moot in light of the Board's conclusion on the nomination issue. By the date on which the Sellers purported to bring the Contract to an end, 26 March 2018, the Buyer had failed to provide the copy charterparty for the Tai Hunter , and so if that were a breach of condition then the Sellers would have been entitled to rely on it. Indeed, the Sellers' message of that date did rely on that failure, and the fact that they did so as evidence of repudiation rather than as a breach of condition may not have mattered (cf Chitty on Contracts , 33 rd ed., § 24-014 "No reason or bad reason given" ).
As the Sellers point out, parties are entitled to see some words in an award that indicate how an issue has been addressed and the reasons for deciding it in the way in which it was decided. On balance, I am persuaded that the Board failed to address this particular issue.
The Sellers submit that in those circumstances I should remit the issue to the Board, citing Popplewell J's statement (summarising existing authority) in Reliance Industries v Union of India [2018] 1 Ll. Rep 562 § 14(7) that:
In the present case, however, the Sellers have raised the same issue by an appeal under section 69 of the Act, for which permission has been given. In those circumstances, I do not consider it necessary or proportionate for the court to decline to determine the point.
No authority has been cited as to whether or not an obligation promptly to provide a copy of the charterparty for a nominated vessel is a condition of the Contract. Moreover, the issue in the present case would be whether a failure promptly to provide the copy charterparty relating to an initial invalid nomination is a breach of condition, even if the buyer was in a position in due course to make a timely valid nomination and to provide a copy of the charterparty relating to that fixture. In my view the answer to that question is no.
A cogent argument could be made that it is a condition of the contract that a copy charterparty for the effective nomination must at least at some stage be provided. As the Buyers point out, under GAFTA § 6 (quoted earlier) a buyer who has made a valid nomination (at least) has the right to make a substitute nomination at any time up to one business day before the estimated time of arrival of the original vessel. An argument might be advanced that failure to provide the copy charterparty by that date would amount to a breach of condition, in light of the likely commercial consequences of the failure (e.g. the seller remaining uninformed of the charterparty provisions relating to matters such as demurrage).
However, it is unnecessary to resolve that point in the present case. On any view, it would be clearly illogical to hold that the buyer could be in breach of condition for failing promptly to provide a copy of the charterparty relating to what might well turn out not to be the effective nomination. Moreover, as the present Buyers point out, there is an obvious risk in chain transactions that delays may be incurred in passing copy documentation down the chain. I very much doubt that commercial parties would have intended any such delay to render the contract liable to immediate termination.
The Sellers point out that it would likely to be difficult to assess damages for breach of the obligation to provide a copy of the charterparty, and such difficulty was listed by Lord Lowry in Bunge as an indication in favour of a term being a condition (citing McDougall v Aeromarine of Emsworth [1958] 1 WLR 1126, 1133). That factor would, however, apply to a great many contractual terms, many or most of which would not be regarded as conditions. It is likely to have weight only when set alongside other considerations pointing in favour of the term in question being a condition. There are in my view no such considerations here.
I conclude that failure to provide a copy charterparty immediately upon the seller's request following nomination of a vessel is not per se a breach of condition; and, specifically, that the failure to provide a copy charterparty for the Tai Hunter prior to the date on which the Buyers nominated a substitute vessel was not a breach of condition.
In these circumstances, the Board's failure fully to address the copy charterparty issue has not caused and will not cause substantial injustice to the Sellers, and thus does not constitute a serious irregularity within section 68 of the Act. I therefore dismiss both the section 68 challenge and the section 69 appeal on this issue.
(F) SECOND SECTION 68 ISSUE: CUMULATIVE EFFECT OF BREACHES
The basis of this challenge is set out in § 26.ii) above.
The Board in its section 57 response, on this point too, took the view that all issues put to it had been addressed, either expressly or by referral to those issues within the body of the Award.
The Buyers point out that the Sellers sought permission to appeal on a question of law corresponding to this section 68 ground. Teare J refused permission on the basis that it was not a point of general public importance and:
The Buyers submit that the Sellers should not be allowed to circumvent that decision via a section 68 challenge. However, Teare J's conclusion that any finding in Buyers' favour was not obviously wrong does not mean that the decision was bound to go in the Buyers' favour.
I am not persuaded that the Board did in fact address its mind to the distinct question of whether, taken together, the four matters relied on by the Sellers in this context (and recited in Award § 9.1) amounted to repudiation/renunciation; nor, in any event, that the Board gave reasons for any conclusion on that point. In practice I think it inconceivable, given the conclusions the Board did reach, that they would have found the cumulative effect of these four matters amounted to repudiation or renunciation: but that does not meet the point, save insofar as it is relevant to the question of substantial injustice.
In order to succeed on the " substantial injustice " test, the Sellers need not show that they would have succeeded on the issue with which the tribunal failed to deal, but only that their position was reasonably arguable: cf Vee Networks Limited v Econet Wireless International [2005] 1 Lloyd's Rep 192 § 40; Home Secretary v Raytheon (cited above) and Konkola Copper Mines v U & M Mining Zambia (No.2) [2014] EWHC 2374 § 19. Though a failure to deal with issues is an irregularity, and will often be a serious irregularity, that is not the case where the claimant's contentions on that issue are not reasonably arguable, so that it cannot be said that any substantial injustice has occurred (see, for an example, Buyuk Camlica Shipping Trading & Industry Co Inc v Progress Bulk Carriers Ltd [2010] EWHC 442 (Comm) ).
The position in summary on each of the four matters, on which the Sellers rely cumulatively, is:
i) the nomination of the Tai Hunter was, the Board found, invalid because the ETA was overly ambitious and the nomination was not made on reasonable grounds: however, the Board found that the Buyers still had ample time to make a valid nomination (and in due course did so);
ii) the initial nomination of the Tai Hunter failed, it appears, to state the name of that vessel's owners: however, that failure was of no consequence because the Tai Hunter nomination could still be (and was) replaced;
iii) there was no finding of breach in relation to the allegation that the Tai Hunter had not been fixed, by the date of its nomination, by the Buyers or their sub-buyers; and
iv) the Board found the Buyers' failure to provide a copy of the charterparty relating to the Tai Hunter at the Sellers' first request to be a breach of contract: however, that failure was also of no consequence for the same reason as indicated in (ii) above.
A series of individually non-repudiatory breaches can cumulatively amount to a renunciation or repudiation of a contract (see, e.g., Force India Formula One Team Ltd v Etihad Airways PJSC [2010] EWCA Civ 1051 § 87); but it remains necessary to establish that the cumulative effect of the various breaches actually passes the threshold for repudiation or renunciation.
As to repudiation, Chitty § 24-041 states inter alia:
Renunciation requires a refusal to perform, or acts/omissions such as to lead a reasonable person to conclude that the party no longer intends to be bound by the contract's provisions; and it must be plain and unequivocal (see, e.g., Chitty §§ 24-018 and 24-019).
In my judgment it is not reasonably arguable that the matters referred to in § 103 above amounted to repudiation or renunciation of the Contract, particularly in circumstances where the Board did not find the nomination of the Tai Hunter to have been made in bad faith, and the Board found that, as at the date of the Sellers' purported termination, the Buyers had ample time to make a valid nomination in its place. I do not consider that the Board could, on any remission, properly hold to the contrary.
I therefore consider that the irregularity did not cause, and will not cause, substantial injustice and therefore does not amount to a serious irregularity within section 68 of the Act. I accordingly dismiss the second section 68 challenge.
(G) APPEAL QUESTIONS 4 AND 5: INTEREST
The interest questions can be taken relatively succinctly. The Sellers say that the Board's conclusion that interest should run from 4 April 2018 was obviously wrong as the payment to the Buyers only arose "in the event [of a] final and unappealable arbitration award". That time has not yet arrived and accordingly, they say, the Buyers are not yet entitled to interest. The Sellers make the following points:
i) Interest is awarded not to punish the defendant but to compensate the claimant for being kept out of the money it is owed: BP Exploration Co (Libya) Ltd v Hunt (No. 2) [1979] 1 WLR 783, 845-846.
ii) The basic rule is that interest is awarded from the date of loss: Kuwait Airways v Kuwait Insurance [2000] Ll. Rep IR 678, 685-686 (where the learned judge goes on to cite three main exceptions to this rule, all of which involve payment from a later date than the date of loss).
iii) Here, the Buyers have not been kept out of their money until the Board's decision becomes unappealable, and certainly not since 4 April 2018. Under § 3(a) of the Settlement Agreement (quoted in § 14 above), the Sellers did not become due to make any payment to the Buyers until their "first request" following the arbitration award becoming final and unappealable. That time has not yet arrived. Accordingly, no interest should have been awarded.
The Buyers say that this is a question of construction of the Settlement Agreement, and that the Board was well placed to address such questions against the relevant background having heard and considered all the evidence (see Russell on Arbitration 8-140).
In my view, the natural construction of the Settlement Agreement leads to the conclusion that interest should run from 4 April 2018.
Clause 3(a) provides that, if the Sellers are found unlawfully to have terminated the Contract, then the Buyers will be considered to have "overpaid" and will be "reimburse[d]". "Overpaid " is in the past tense and "reimburse" connotes repayment of a sum previously paid over. Both expressions tend to suggest that the parties recognised that in such circumstances the Buyers would have been kept out of their money as from the original payment of the price. That view also reflects the commercial reality of the situation. The parties were not replacing a damages claim with future contractual rights: they were in essence varying the purchase price paid on 4 April 2018. The adjustment mechanism in § 3 will reflect that reality only if interest is backdated so as, as nearly as possible, to put the Buyers in the position in which they would have been had the appropriate price been paid at the time.
Accordingly, I do not consider that the award of interest is in any way punitive. It simply reflects the real loss suffered by the buyers. The Board had a broad discretion to award interest from such dates, at such rates and with such rests as it considered met the justice of the case (section 49(3) of the Arbitration Act 1996); and I do not consider that its decision discloses any error of law or approach. On the contrary, it reflects in my view a sensible construction of the Settlement Agreement.
(H) CONCLUSION
It follows that I dismiss all of the section 69 and 68 challenges and uphold the Award.